Wheatlyn Medical

Wheatlyn Medical – Paragon Engineering Services was hired by the Mechanical Contractor to provide a 3D Revit MEP Coordination model and drawings for a 22,600 sq.ft. single story medical building. The mechanical system consisted of a 60 ton Packaged Industrial DX Cooling with Hot Water Heat Rooftop Unit, two boilers in a mechanical room, and zoned hot water heat single duct terminal VAV boxes. Coordination consisted of all piping (plumbing, heating, storm water), plumbing and mechanical equipment, hvac ductwork, lighting, and working with the sprinkler contractor for the wet pipe sprinkler system. This is the first project in the York, Pa area where all parties hired, worked together to create a single 3D Revit BIM Model for coordination purposes.

Paragon’s Services Included:

  • MEP Coordination
Project Leader Thomas Rumsey